The positioning of 20 metallic support structures in « La vallée de La ROYA » undertaken by ENEDIS CAZ.
Objective
ENEDIS CAZ, Nice approached us with the request for the positioning of approximately twenty 225kV supports.
As the zone was rated inaccessible, high level tension experts were required for this type of intervention.
Proposition
Use of a B3 helicopter for the supply of equipment and Super Puma for the laying down of support structures.
Supports already in the horizontal position were lifted accordingly , and those not able to be hoisted, were equipped with assembly kits.
Respecting high levels of security and low risk of injury no employees were involved directly with the support structures during helicopter operations.
An exterior company to RTE will be on site for operations in order to manage the technical operations of the removal of materials
Airtelis operational team :
- A Sales department representative and Project Leader from Airtelis ;
- Technicalities to be managed by OMEXOM, assisted by the RTE/STH Works Division for helicopter operations, and further verifications.